Power Plant
Projects
| REFERENCE PROJECT |
|
Customer:
Kumpuniemen Voima, Suolahti, Finland
Project:
Turnkey Delivery of 3.7 MW Steam Turbine Plant
Order:
1993
Take-Over:
1994
|
 |
| |
Energico's Services:
- main contractor functions
- engineering and coordination
of deliveries
- erection
- commissioning and trial run
- site management
and supervision
Energico's Scope of Supplies:
- steam turbine (Peter Brotherhood)
- generator (Brush Electrical
Machines)
- district heating system
- vacuum and condensate system
-
piping and insulation |
| |
| Main Data of the
Turbine Plant |
| Fuel: |
Wood Chip |
|
Parameters:
|
|
| - live steam flow rate |
7 kg/s |
| - live steam pressure |
42 bar |
| - live steam temperature |
480 °C |
| - extraction steam pressure |
16 bar(a) |
| - extraction steam temperature |
370 °C |
| - exhaust steam pressure |
0,65 bar(a) |
| - electrical output |
3 700 kW |
| - district heating output |
10 850 kW |